← 실적 발표
LNT FY2025 Q4 개선

Alliant Energy Corporation 실적 발표

Feb 20, 2026 · 10:00 ET Lisa BartonRobert DurianSusan Gill earningscall_biz
Buzzberg 분석

QTS project relocated to Iowa with new ESA signed

Alliant Energy reported FY2025 EPS growth of 6% y/y and affirms 2026 guidance, with 7%+ EPS CAGR target for 2027-2029. The key update is that QTS's Wisconsin data center project (Greater Madison) has been relocated to Iowa and a new ESA was signed, with capex reallocated between gas/renewables and between the Iowa/Wisconsin utilities. Regulatory constructs in Iowa (flat base rates through 2030) and Wisconsin (individual customer rate filings) are facilitating this load growth while management emphasized safeguards so existing customers don't pay for data center expansion. FY2025 ongoing EPS of $2.85, up 6% y/y vs guidance midpoint, with a dividend increase (22nd consecutive year).

Buzzberg 분석 QTS project relocated to Iowa with new ESA signed Alliant Energy reported FY2025 EPS growth of 6% y/y and affirms 2026 guidance, with 7%+ EPS CAGR target for 2027-2029. The key update is that QTS's Wisconsin data center project (Greater Madison) has been relocated to Iowa and a new ESA was signed, with capex reallocated between gas/renewables and between the Iowa/Wisconsin utilities. Regulatory constructs in Iowa (flat base rates through 2030) and Wisconsin (individual customer rate filings) are facilitating this load growth while management emphasized safeguards so existing customers don't pay for data center expansion. FY2025 ongoing EPS of $2.85, up 6% y/y vs guidance midpoint, with a dividend increase (22nd consecutive year). 전체 분석 보기분석 접기

Alliant Energy reported FY2025 EPS growth of 6% y/y and affirms 2026 guidance, with 7%+ EPS CAGR target for 2027-2029. The key update is that QTS's Wisconsin data center project (Greater Madison) has been relocated to Iowa and a new ESA was signed, with capex reallocated between gas/renewables and between the Iowa/Wisconsin utilities. Regulatory constructs in Iowa (flat base rates through 2030) and Wisconsin (individual customer rate filings) are facilitating this load growth while management emphasized safeguards so existing customers don't pay for data center expansion. FY2025 ongoing EPS of $2.85, up 6% y/y vs guidance midpoint, with a dividend increase (22nd consecutive year).

  • Four executed ESAs totaling 3 GW of peak load (50% future growth); actively seeking 2-4 GW additional load.
  • QTS relocated its 200+ MW data center from Wisconsin to Iowa; new ESA signed and ramp delayed <1 year; capex plan maintained at ~$13.4B.
  • Capital plan shifted from gas combined-cycle to simple-cycle and added Iowa wind; gas turbines reserved for all planned simple-cycle builds.
매출$1.064B보고값
주당순이익(EPS)$0.60보고값
매출총이익률42.01%보고값
영업이익률18.42%보고값
근거 있는 핵심 내용 6개

지금 중요한 점

이번 발표에서 가장 의미 있는 변화를 정리했습니다.

01
Demand

QTS project relocated to Iowa with new ESA signed

02
Demand

Four ESAs totaling 3 GW of peak load

03
Demand

Pursuing additional 2-4 GW of large load growth

핵심 내용 3개 더 보기
04
Regulatory

No active rate reviews planned in 2026

05
Guidance

Long-term EPS growth of 7% plus expected 2027-2029

06
Capex

Completed 275 MW of energy storage in 2025

보고 기간

보고 실적

지표보고값변화
매출$1.064B보고값
주당순이익(EPS)$0.60보고값
매출총이익률42.01%보고값
영업이익률18.42%보고값
잉여현금흐름$-2.214B보고값
자본지출$2.483B보고값
향후 전망

향후 가이던스

지표기간범위중간값상태
주당순이익(EPS)FY2026$2.92–$3.08컨센서스 부합$3.00유지
AI, 자본지출 및 수요 분석

경영진 분석

Confident

Management expressed confidence in their ability to pivot and execute on growth opportunities, highlighting the 'Alliant Energy Advantage' and constructive regulatory outcomes.

자본지출

투자 및 생산능력

Alliant Energy's consolidated four-year capital plan remains on track at approximately $13.4 billion, with investments reallocated between states and technologies (gas, wind, storage) to support data center load. The plan includes simple cycle gas resources, renewables, and energy storage, with proactive safe harboring of tax credits and secured turbine reservations to ensure execution certainty.

아래에 언급된 기업 4개 모두 표시

기업발표 이후 수익률

고객

고객

QTS dropped its Madison, Wisconsin site and moved the load to Iowa, showing its project needs are location-flexible within Alliant's territory but that site-level issues can cause pivots.

근거
“QTS, one of the data center customers we serve, made the decision to relocate its Greater Madison, Wisconsin data center project. After assessing multiple sites within our service area, QTS has selected a new location within our Iowa”
Lisa Barton

공급망

공급망

Alliant has secured gas turbine reservation agreements for all planned self-developed gas resources, locking in supply early to execute simple-cycle builds quickly. — Confirms turbine slot availability for near-term capacity builds, signaling gas turbine suppliers have lock-step demand into 2026-2027.

근거
“We have secured gas turbine reservation agreements and project locations for all planned self-developed gas resources.”
Robert Durian
공급망

Alliant has proactively safe-harbored renewable/storage projects amid evolving tax legislation, preserving tax credit eligibility and flexibility. — Proactive safe-harboring supports the renewal of federal tax credits, effectively lowering delivered cost of renewables and pulling forward capex eligibility.

근거
“We proactively protected future customer investments by safe harboring planned renewable and energy storage projects amid evolving tax legislation, preserving flexibility.”
Lisa Barton
외부 신호

공급망 알파 · 4발표 이후 수익률

A1

The QTS relocation shifted $ capital from gas generation to renewables (wind) within the Iowa/Wisconsin capex plan, adding Iowa wind within the advanced rate-making proposal.

근거
“Most of the recent shift... was just a shift between what we call gas generation to renewables. There's also some shift between our Wisconsin utility to our Iowa utilities that coincide with the relocated load.”
A2

Alliant has secured gas turbine reservation agreements for all planned self-developed gas resources, locking in supply early to execute simple-cycle builds quickly.

A3

Alliant has proactively safe-harbored renewable/storage projects amid evolving tax legislation, preserving tax credit eligibility and flexibility.

A4

Iowa's regulatory construct allows base rates to stay flat through the decade while individual customer rate contracts absorb fixed costs, a pace-setting model for peer utilities.

근거
“we are trying to extend that over a longer period of time.”
방법론 및 범위

경영진 발언만 분석합니다. 검증된 기업 언급 4개를 모두 표시하며, 보고 실적과 향후 가이던스를 분리합니다. 공개 근거는 화자가 표시된 짧은 인용문 8개로 제한됩니다. AI 분석은 불완전하거나 틀릴 수 있으므로 중요한 주장은 원문에서 확인하세요.