FCX FY2025 Q3 IN LINE

Freeport-McMoRan, Inc. 실적 발표

Nov 18, 2025 · 05:00 ET Corey StevensDavid JointKathleen Quirk
Buzzberg 분석

Grasberg Block Cave restart delayed to Q2 2026 for PB2/PB3, PB1S mid-2027, PB1C end-2027.

Freeport-McMoRan held a special earnings call to detail the investigation into the September 8 mud rush incident at the Grasberg Block Cave that killed seven workers. Management explained the unique geological and operational factors that caused the event, outlined a phased restart plan (PB2/PB3 by Q2 2026, PB1 South mid-2027, PB1C end-2027), and discounted any impact on other mines. No cross-company signal was provided; the call focused on internal safety and remediation. The incident was caused by an undetected high-velocity flow zone that connected a draw point to a 300-meter column of mud accumulated in the former open pit, with a 5-10x increase in flow velocity.

Buzzberg 분석 Grasberg Block Cave restart delayed to Q2 2026 for PB2/PB3, PB1S mid-2027, PB1C end-2027. Freeport-McMoRan held a special earnings call to detail the investigation into the September 8 mud rush incident at the Grasberg Block Cave that killed seven workers. Management explained the unique geological and operational factors that caused the event, outlined a phased restart plan (PB2/PB3 by Q2 2026, PB1 South mid-2027, PB1C end-2027), and discounted any impact on other mines. No cross-company signal was provided; the call focused on internal safety and remediation. The incident was caused by an undetected high-velocity flow zone that connected a draw point to a 300-meter column of mud accumulated in the former open pit, with a 5-10x increase in flow velocity. 전체 분석 보기분석 접기

Freeport-McMoRan held a special earnings call to detail the investigation into the September 8 mud rush incident at the Grasberg Block Cave that killed seven workers. Management explained the unique geological and operational factors that caused the event, outlined a phased restart plan (PB2/PB3 by Q2 2026, PB1 South mid-2027, PB1C end-2027), and discounted any impact on other mines. No cross-company signal was provided; the call focused on internal safety and remediation. The incident was caused by an undetected high-velocity flow zone that connected a draw point to a 300-meter column of mud accumulated in the former open pit, with a 5-10x increase in flow velocity.

  • Phased restart: PB2 and PB3 resume in Q2 2026 after cement plugs isolate PB1C; PB1 South targeted mid-2027 (chute repairs); PB1C deferred to end-2027.
  • Other mines (Deep MLZ, Big Gossan, Kucing Liar) have no similar risk and have already restarted; the Grasberg incident does not affect development of Kucing Liar.
  • 2026 copper production expected similar to 2025; production rises to ~1.5bn lbs in 2027 and ~1.7bn lbs in 2028-2029 (small contribution from PB1C at 2-3%).
Revenue $6.972B reported
EPS $0.50 reported
Gross margin 29.93% reported
Op margin 28.06% reported

이번 분기에 달라진 점

01
Guidance

Grasberg Block Cave restart delayed to Q2 2026 for PB2/PB3, PB1S mid-2027, PB1C end-2027.

Guidance tone

02
Guidance

Production in 2026 expected similar to 2025, with significant increases in 2027-2029.

Guidance tone

03
Operations

Incident caused by undetected surface mud connection, not human error or water management failure.

Phased restart: PB2 and PB3 resume in Q2 2026 after cement plugs isolate PB1C; PB1 South targeted mid-2027 (chute repairs); PB1C deferred to end-2027.

04
Operations

Cement plugs and surface mud mitigation key to safe restart.

Other mines (Deep MLZ, Big Gossan, Kucing Liar) have no similar risk and have already restarted; the Grasberg incident does not affect development of Kucing Liar.

수요 및 자본지출

수요

수주 및 전환

Management expresses confidence in the long-term recovery and value of Grasberg, but the near-term production impact and tragic incident temper the tone. The phased restart plan is laid out with clear milestones, but no upward revision to overall guidance.

자본지출

투자 및 생산능력

Management cut capital expenditure guidance by approximately $800 million for 2025-2026, deferring spend to prioritize the Grasberg recovery. They added a placeholder of roughly $250 million for equipment replacement and damage, and expect up to $700 million in insurance coverage for underground losses.

톤 · Measured, Resolute

Management acknowledged the tragedy and technical uncertainty, but projected confidence in a phased, safety-first restart with long-term production recovery and growth.