D FY2026 Q2 IMPROVING

Dominion Energy, Inc. earnings call

Jul 31, 2026 · 11:00 ET Bob BlueDavid McFarlandEd Bain
Buzzberg read

CVOW cost estimate raised to $11.65 billion, schedule pushed to end-2027

Dominion Energy reaffirmed its full-year guidance, driven by strong data center demand (53 GW pipeline) and progress on the massive offshore wind project. The company updated the offshore wind completion timeline to end-2027 (six-month delay) and marginally raised the cost estimate to $11.65B, but emphasized the project is largely de-risked and already generating power. Management also provided updates on the NextEra merger and new gas plant filings. Reaffirmed FY2026 operating EPS, credit, dividend, and long-term growth guidance.

Buzzberg read CVOW cost estimate raised to $11.65 billion, schedule pushed to end-2027 Dominion Energy reaffirmed its full-year guidance, driven by strong data center demand (53 GW pipeline) and progress on the massive offshore wind project. The company updated the offshore wind completion timeline to end-2027 (six-month delay) and marginally raised the cost estimate to $11.65B, but emphasized the project is largely de-risked and already generating power. Management also provided updates on the NextEra merger and new gas plant filings. Reaffirmed FY2026 operating EPS, credit, dividend, and long-term growth guidance. Read full analysisCollapse analysis

Dominion Energy reaffirmed its full-year guidance, driven by strong data center demand (53 GW pipeline) and progress on the massive offshore wind project. The company updated the offshore wind completion timeline to end-2027 (six-month delay) and marginally raised the cost estimate to $11.65B, but emphasized the project is largely de-risked and already generating power. Management also provided updates on the NextEra merger and new gas plant filings. Reaffirmed FY2026 operating EPS, credit, dividend, and long-term growth guidance.

  • Q2 2026 operating EPS of $0.79, including $0.03 of RNG credits.
  • Data center demand remains strong; now 53 GW in contracting pipeline, 12 GW contracted.
  • Offshore wind project 81% complete; final turbine now expected by end of 2027.
Revenue $4.558B -11% QoQ
EPS $0.79 -17% QoQ
Gross margin 49.67% reported
Op margin 23.48% reported

What changed this quarter

01
Capex

CVOW cost estimate raised to $11.65 billion, schedule pushed to end-2027

Management updated the Coastal Virginia Offshore Wind project cost estimate to $11.65 billion, reflecting a net increase of ~2% due to schedule extensions and additional costs, while emphasizing the project's de-risking and regulatory cost recovery progress. They also mentioned…

02
Construction

Offshore wind project 81% complete, 31 turbines installed

Reaffirmed FY2026 operating EPS, credit, dividend, and long-term growth guidance.

03
Demand

Data center capacity in pipeline grew 11% to over 53 GW

Management repeatedly expressed confidence in achieving financial commitments, highlighted strong first-half results, and emphasized the de-risking of the offshore wind project despite schedule delays.

04
M&A

NextEra merger regulatory filings submitted, hearings in late 2026

Data center demand remains strong; now 53 GW in contracting pipeline, 12 GW contracted.

Demand & capex

Demand

Bookings & conversion

Data center capacity in pipeline grew 11% to over 53 GW. Management repeatedly expressed confidence in achieving financial commitments, highlighted strong first-half results, and emphasized the de-risking of the offshore wind project despite schedule delays.

Capex

Investment and capacity

Management updated the Coastal Virginia Offshore Wind project cost estimate to $11.65 billion, reflecting a net increase of ~2% due to schedule extensions and additional costs, while emphasizing the project's de-risking and regulatory cost recovery progress. They also mentioned ongoing investments in transmission infrastructure, new gas-fired combined cycle plants, and battery storage, with the fi

Tone · Confident

Management repeatedly expressed confidence in achieving financial commitments, highlighted strong first-half results, and emphasized the de-risking of the offshore wind project despite schedule delays.

Supply-chain alpha

A1

Dominion Energy's offshore wind project completion timeline slipped by 6 months to end of 2027, with a $288M cost increase, but the extra quarterly cost is now below the prior 'rule of thumb' guidance.

“we've added about $288 million to account for the incremental two quarters to complete the final turbine installation. You'll note that this averages out to about $144 million per additional quarter, which is below the low end of our prior…”
Bob Blue
A2

Dominion Energy now has 53 GW of data center capacity in various stages of contracting, up 11% since year-end, with 12 GW contracted under ESAs.

“We now have over 53 gigawatts of data center capacity in various stages of contracting, including approximately 12 gigawatts of capacity contracted under electric service agreements”
Steven Ridge
A3

A recent grid disruption in Virginia caused some data centers to switch to backup power, and while rare, mitigation will mostly involve incremental 'lessons learned' rather than significant new investment.

“we have and will continue to collaborate closely with these customers to identify other mitigation opportunities. We've been sharing information and will continue to do so and implement lessons learned. We don't feel like there's significa…”
Bob Blue

Forward guidance

ImprovingGuidance tone · was IN LINE last Q
Forward guidance
MetricPeriodRangeMidpointStatus
CapexOFFSHORE_WINDFY2027$11.65B$11.65BRAISED

Company read-throughs

-3.6%
since call
$87.56$84.40
PartnersSupply-chain alpha

Dominion Energy's offshore wind project completion timeline slipped by 6 months to end of 2027, with a $288M cost increase, but the extra quarterly cost is now below the prior 'rule of thumb' guidance. — This indicates the project was completed ~82% right before the end of Q2 and that installation efficiency is improving, reducing the risk of further slippage; with the merger, a delay here directly impacts the combined entity's cash flow profile.